News Centre

Keyword search

22

2019 - 4

Henan Bohai Chemical Co., Ltd. Desulfurization Regeneration Liquid Treatment and Comprehensive Utilization Project

I. Project Name and Overview

       Project Name: Desulfurization Regeneration Liquid Treatment and Comprehensive Utilization Project of Henan Bohai Chemical Co., Ltd.

       Project nature: New

       Construction site: Henan Bohai Chemical Co., Ltd., Huling Industrial Cluster Area, Jiyuan City

       Total investment: 849.09 million yuan

       Project record: 2019-419001-26-03-014869

       Construction Content: Annual treatment and comprehensive utilization of 30,000 tons of desulfurization regeneration liquid.

       The route is:

  1. Pretreatment process: The desulfurization regeneration
    liquid is sent to a horizontal centrifuge for solid-liquid separation, the
    filtrate enters the filtrate tank, the sulfur paste enters the slurry tank, and
    then is sent to the incineration process by the slurry transfer pump.
  2. Incineration process: After the sulfur slurry is atomized, it is sent to the incinerator to generate SO2 process gas, and enters the waste heat boiler for waste heat recovery. The process gas is cooled and then enters the purification process.        
  3. Purification process: The process gas passes through the humidification tower, the cooling tower, the washing tower and the electric mist eliminator in turn, respectively humidifying and cooling the process gas, cooling the gas, washing, and then entering the dry suction process.        
  4. Dry suction process: The drying of the furnace gas is achieved by contacting the gas with concentrated sulfuric acid. After SO2 is converted into SO3, it enters the absorption tower and absorbs SO3 with concentrated sulfuric acid to produce sulfuric acid of different specifications.        
  5. Conversion process: The process gas enters the process gas heat exchanger after being pressurized by the fan, and reaches the SO2 converter after reaching 420 ° C to 450 ° C. Under the action of the catalyst, the SO 2 is converted into SO 3 .        
  6. The tail suction process: the tail gas enters the tail gas washing tower, and a small amount of SO2, NOX and sulfuric acid mist are absorbed by the steamed ammonia wastewater, and the tail gas from the tail gas washing tower enters the electric mist eliminator to further capture the acid mist entrained in the tail gas. After passing the test, it is discharged into the atmosphere through the chimney.

The main equipments are: horizontal centrifuge, incinerator, waste heat boiler, drying tower, absorption tower, humidification tower, cooling tower, washing tower, exhaust gas cleaning tower, sulfur dioxide blower, etc.

II. The construction unit and contact information       

Construction unit: Henan Bohai Chemical Co., Ltd.       
Contact: Chen Zhanqun       
Contact number and fax: 0391-6038009
Email: jmjhch@163.com


III. The unit responsible for environmental impact assessment unit and contact information      

EIA unit: Henan Metallurgical Research Institute Co., Ltd.       
Contact: Zhou Gong       
Contact number and fax: 0371-63828676       
Contact Email: yjshps@163.com       

IV. Environmental impact assessment program and main work content

  1. EIA work program

       (1) Accept the entrustment of environmental impact assessment work.

       (2) Conduct the first EIA information disclosure and seek public opinions.

       (3) Carry out construction project analysis and conduct investigation, monitoring and evaluation of environmental conditions within the scope of evaluation.

       (4) Forecasting and evaluating the environmental impacts of various environmental factors, and analyzing and evaluating the environmental impacts of each topic.

       (5) Give the evaluation conclusions of the feasibility of the construction project environment, propose environmental protection measures and recommendations, and carry out technical and economic certification.

       (6) Prepare environmental impact assessment files, and after the formation of the consultation draft, conduct the second EIA information disclosure to solicit public opinions.

       (7) Before the approval of the environmental impact report to the competent department of ecological environment, the third EIA information disclosure, the full report of the public report and the public participation instructions.

  1. Environmental impact assessment work content and key points

       The environmental impact assessment mainly analyzes the pollution production and sewage discharge of the project, predicts the impact of pollution, evaluates whether the pollution prevention measures are feasible, the clean production level of the project, the rationality analysis of the site and the total control target, according to the profile of the project. Corresponding monitoring management plans, conclusions of environmental impact assessment, public participation instructions, etc.

The environmental impact assessment work will focus on the impact of the project on the atmospheric environment, water environment and environmental risks on the basis of the principles of “standard discharge, clean production, and total control”, and propose measures to mitigate the mitigation measures.

 

V. The scope and main issues of seeking public comments

Scope: Enterprises, units, and residents located in the evaluation area.

Main items: opinions and suggestions on project construction, opinions and suggestions on project environmental protection measures and impact mitigation measures, issues to be concerned in project construction/operation and other opinions and suggestions that need to be explained.

VI. Public comments channels

       After the information is publicized, the public may send an e-mail, telephone, letter or other convenience to the designated address to express opinions on the construction of the project and the EIA work. The opinion form can be downloaded from the link.

       During the preparation of this project environmental impact report, the public may submit opinions and suggestions related to environmental impact assessment to the construction unit and the EIA unit.

       Attachment: Public Comment Form.docx

7

2019 - 3

Henan Jinma Energy Co., Ltd. - The first public announcement of the environmental impact assessment of with an annual output of 1.6 million tons of coking project

 (I) Project Overview

      Henan Jinma Energy Co., Ltd. (hereinafter referred to as “Jinma Energy”) has an annual output of 1.6 million tons of coking project located in the Chemical Industry Park of Huling High-tech Industrial Development Zone in Jiyuan City. It has passed 600,000 tons of Yugang (Jiyuan) Coking Group Co., Ltd. The annual tamping coke oven was relocated to the city to relocate, and the two existing 4.3-meter coke ovens (1 million tons/year capacity) of Jinma Energy were upgraded, 1.6 million tons/year coking project was built, and the downstream industrial chain was extended. . At present, the project has been filed in the Huling Industrial Cluster Zone of Jiyuan City, and the project code is 2018-419001-25-03-072006.

 

The project mainly consists of a reheating top-loading coke oven with a height of 7m in a 2×70-hole carbonization chamber, as well as supporting facilities such as coal preparation, coke treatment system, CDQ, gas purification system and coking wastewater pretreatment. Facilities, etc.

 

Jinma Energy has two JNK43-98D 72-hole tamping coke ovens (1 million t/a coking project) and JNDK55-05 tamping coke ovens (900,000 t/a coking project), with coal preparation , coking, chemical recovery, comprehensive utilization of gas, cogeneration system and 13 km long railway line and water, electricity, gas and other public and auxiliary facilities. The existing engineering environmental protection facilities are well-equipped, and the exhaust gas treatment measures mainly include coal loading ground dust removal station, push-focus ground dust removal station, dry quenching ground dust removal station, coke oven flue gas desulfurization and denitration system, VOCs treatment facilities, etc. Can achieve standard discharge;


The wastewater treatment facilities mainly include a 120m3/h phenol cyanide wastewater treatment station, a 160m3/h wastewater treatment station, and a 350m3/h water reuse treatment station, which is responsible for processing the existing 1 million t/a coking project, 90 The 10,000 t/a coking project produces domestic wastewater, and the coke granule pure oxygen gas project is used to produce domestic wastewater. At the same time, it also receives the production and domestic wastewater of Jinjiang Refinery and Jinyuan Chemical Company for treatment. After the whole plant wastewater treatment, it will be reused and not discharged. For the noise sources of the existing projects, indoor placement, vibration reduction, sound insulation and noise reduction are adopted. The noise of the factory boundary is up to standard; the solid waste generated by the existing projects mainly includes The tar residue, excess sludge, dust collector dust, coke powder, etc., all solid wastes are comprehensively utilized and properly disposed of, and are not discharged into the environment.

 


(II) Name and contact information of the construction unit       

Construction unit: Henan Jinma Energy Co., Ltd.;       
Contact person: Chen Gong;       
Contact number: 0391-6038009;       
E-mail: jmjhch@163.com       
Address: Chemical Industry Park, Huling High-tech Industrial Development Zone, Jiyuan City.

     
(III) Name of the organization of the environmental impact report       

EIA unit: Henan Metallurgical Research Institute Co., Ltd.;       
Contact person: Liu Gong;       
Contact number: 0371-63827039;       
E-mail: yjshps@163.com;       
Address: No.1, No. 4, Huanghe North Street, Jinshui District, Zhengzhou City.

 

(IV) Public comments channels      

The public may download the public participation opinion form from the attached post, fill in the suggestions and opinions related to the environmental impact and environmental protection measures of the project, and then return it to the construction unit or the EIA unit by mail or by e-mail.      In the process of preparing the draft of the environmental impact report, the public may submit opinions related to the environmental impact assessment to the construction unit.       

Attachment: Public Comment Form.docx

10

2019 - 1

Yang hongying, President of the bank of communications henan branch, and her colleagues are in the company

On January 10, 2019, Yang hongying, President of henan branch of bank of communications, visited our company